Case Study: Chiswell Green, Herts

The Overview.

Chris wanted to transform a modest bungalow plot into a substantial, high-quality family home, without personally managing the complexity of planning, design coordination and construction delivery.

We guided the project from concept through to completion, managing planning negotiations, technical development and full construction delivery. The result is a six-bedroom residence defined by scale, detail and long-term performance, delivered with structured oversight and disciplined execution throughout.

Location

Chiswell Green, Herts

Project Type

Full Design and Build. Complete redevelopment of an existing bungalow plot into a high-specification three-storey 6-Bed, 6-Bath family residence.

Key Challenge

Securing planning consent for a significantly larger home while coordinating a technically detailed, high-performance specification.

Build Duration

11 months from demolition to completion.

The Challenges & Solutions

The Ragged Hall Lane project required careful planning negotiation and disciplined coordination to transform a modest bungalow plot into a substantial three-storey residence. Securing approval for a significantly larger home demanded a considered design approach and proactive engagement with the local authority to ensure scale, massing and architectural intent were aligned with planning expectations from the outset.

Beyond planning, the brief called for a home of exceptional quality and long-term performance. Chris was particularly sensitive to sound transfer and wanted the internal environment to feel calm and quiet, regardless of the home’s size and activity. In response, we designed the structure with solid internal walls, enhanced floor construction and carefully specified materials to reduce sound movement throughout the house. This performance-led thinking was integrated from the early design stages rather than treated as an afterthought.

Delivering this level of detail required close coordination between structural, mechanical and specialist suppliers. Underfloor heating across two floors, high-specification finishes and a technically robust envelope were all carefully managed to ensure both comfort and durability. Through structured oversight from design development through to construction delivery, we maintained quality control and programme discipline across the 11-month build.

The result is a substantial, detail-driven family home that balances scale with comfort, presence with performance.

Learn more about our approach

Project Stages and Timeframes

Discover
Opinion of Probable Cost (OPC)
Typically 1–2 weeks
  • High-level benchmarked cost assessment
  • High-level programme overview
  • Clear next-step roadmap
Define
Feasibility Study
Typically 4–6 weeks
  • Planning and policy review
  • Site and technical assessment
  • Bespoke Project Management Software activated
  • Specification alignment
  • Budget validation
  • Feasibility conclusion and direction
  • Planning application (if not yet approved)
Prepare
Pre-Construction & Technical Coordination
Typically 8–16 weeks
  • Full design coordination
  • Building regulations completion
  • Planning conditions discharge
  • Refined cost plan and procurement validation
  • Programme sequencing and risk mitigation
  • Project team formalised
  • Introduction to Project Coordinator
Deliver
Construction & Handover
Typically project-dependent
  • Dedicated project leadership
  • Dedicated build team assigned
  • Live programme and cost control
  • Variation management through the platform
  • Quality inspections and consultant coordination
  • Structured communication and reporting
  • Professional snagging and handover
Select an item
Click a row to view details

Disclaimer: These are indicative prices for new build houses based on 2025 costings as a rough guide only.